20080606 CP International Reporting Plan
- Rebuild the CP Giftcard database. Estimated time frame: 06 June – 13 June (1 week) - DONE
- Rebuild the Incomm Gamecard database. 13 June – 20 June (1 week) - DONE
- Look at new Global reporting requirements and start reporting against those. 20 June – 18 July. (4 weeks) – ON TRACK
- Document new DB processing and reporting procedures 18 July - 15 August. (4 weeks) - ON TRACK
- Revive the SQL Server reporting project – restate reporting requirements using the new data structure. 15 August - 19 September. (5 weeks). ON TRACK
- (Stretch) Expand Analytics to a new payment type each month:
- May – Added PayPal
- July – Add Giftcards for Beanstream and PayPal
- August - Add PayByCash and Surfpin
- September – Add Manual
- May – Added PayPal